TFL: "Import Failed - Invalid Data File Format"
Problem: When importing a CSV/TXT file the user gets an error stating "IMPORT FAILED - INVALID DATA FILE FORMAT"
Solution: This is caused by the format of the point file being incorrect. The point file must:
- Contain a header (name, N(y), E(x), Z, Description).
- Must contain a ""Description"" column even if it is blank
Related Articles
TFL: Import SKP File NOT Available
TFL: Import SKP File NOT Available Problem: When attempting to import a SketchUp model (SKP), the file is not being displayed in the "Import" menu. Solution: Trimble Field Link only accepts .skp files NOT .SKP files. To resolve, rename the file to ...
FieldLink: Creating a Project and Importing Data v6.3
FieldLink: Creating a Project and Importing Data v6.3 With the release of FieldLink v6.3 the workflow for creating and managing files has changed. You will no longer being creating a Job file inside of FieldLink that stores the project point and scan ...
Trimble FieldLink: Log File
Trimble FieldLink: Log File Problem: User is experiencing a lag, corrupted file, or overall "unique" issues while running TFL. Solution: User may need to change permission settings for ""Folders"": Go to the start menu or Microsoft icon and click on ...
FieldLink: v6.6 Release Notes
FieldLink: v6.6 Release Notes FieldLink v6.6 (2023-02 v6.6.0) has been released and ready to install via Trimble Installation Manager (TIM). Please see the support article about installing updates via TIM if you need help updating FieldLink. Please ...
FieldLink: v6.7 Release Notes
FieldLink: v6.7 Release Notes FieldLink v6.7 (2023-05 v6.7.0) has been released and ready to install via Trimble Installation Manager (TIM). Please see the support article about installing updates via TIM if you need help updating FieldLink. Please ...